ANALYSIS OF DELAYS IN COAL DELIVERY ACTIVITIES AT PT PILAR PUTRA MAHAKAM

Authors

  • Budi Purnomo Banten Merchant Marine Polytechnic
  • Yollanda Octavitri Banten Merchant Marine Polytechnic
  • Pramudyasari Nur Bintari Banten Merchant Marine Polytechnic
  • Moudyna Aisyah Wiliz Banten Merchant Marine Polytechnic

DOI:

https://doi.org/10.53067/ijomral.v4i6.387

Keywords:

Coal, tugboat, shipping, time efficiency

Abstract

One of the shipping activities frequently carried out in the Indonesian shipping industry is coal shipping. Indonesia is one of the world's leading coal mining countries, and the island of Kalimantan is the largest coal producer in Indonesia. Kalimantan Island is one of Indonesia's mining production areas. One of the shipping activities frequently carried out in the Indonesian shipping industry is coal shipping. PT Pilar Putra Mahakam participates in supporting the timely delivery of coal from Senyiur to the North Sulawesi 1 Steam Power Plant. The purpose of this study was to determine the factors causing delays in coal deliveries by the Tugboat Nunukan 1. This study was conducted at PT Pilar Putra Mahakam from August 1, 2024, to July 31, 2025. This study used a descriptive qualitative method with data collection techniques of observation, interviews, and documentation. Data were sourced from primary and secondary sources. The results of this study explain the factors influencing delays in coal deliveries by the Tugboat Nunukan 1 from Senyiur Jetty to PLTU 1, including technical damage to the vessel, inaccurate surveyors during the ship's seaworthiness survey before chartering, and traffic congestion.

Downloads

Download data is not yet available.

References

Indrianto, N., & Supomo, B. (2012). Business research methodology for accounting & management. BPFE Yogyakarta.

Kriyantono, R. (2020). Practical communication research techniques: Accompanied by practical examples of media research, public relations, advertising, organizational communication, and marketing communication. Prenadamedia Group.

Moleong, L. J. (2017). Qualitative research methodology (Revised Edition). PT Remaja Rosdakarya.

Sugiyono. (2018). Educational research methods: Quantitative, qualitative, and R&D approaches. Alfabeta.

Sugiyono. (2019). Qualitative research methods. Alfabeta.

Law of the Republic of Indonesia Number 17 of 2008 concerning Shipping. (2008). State Gazette of the Republic of Indonesia 2008 Number 64. State Secretariat.

Downloads

Published

2025-11-11

How to Cite

Purnomo , B. ., Octavitri , Y. ., Nur Bintari, P., & Aisyah Wiliz, M. (2025). ANALYSIS OF DELAYS IN COAL DELIVERY ACTIVITIES AT PT PILAR PUTRA MAHAKAM . International Journal of Multidisciplinary Research and Literature, 4(6), 1050–1061. https://doi.org/10.53067/ijomral.v4i6.387