ANALYSIS OF COST AND CASTING TIME WITH CONVENTIONAL AND PRECAST METHODS ON THE CITEREUP FLYOVER CONSTRUCTION PROJECT
DOI:
https://doi.org/10.53067/ijomral.v2i2.111Keywords:
Flyover Construction, Precast, Conventional, EfficiencyAbstract
The concrete manufacturing process, also known as casting, is the final stage that determines the success of a flyover construction project. The benchmark lies in the casting method which of course has a direct effect on resource efficiency, processing time, budget, and quality. Generally, the process of casting concrete in flyover construction projects in Indonesia uses the conventional method in which the process is carried out and cast in situ. However, the development of science and the paradigm of efficiency in the dimensions of flyover construction projects has given birth to a new method in which the concrete hardening process can be carried out elsewhere and made precast.The conventional method and the precast method are now the best alternative by taking into account aspects of cost, quality and time which are considered for efficiency in flyover construction projects. For this reason, the researchers analyzed the efficiency of the Citeureup flyover construction project using the concrete casting method used in the process
Downloads
References
Handbook, 2021, PT. Wika Beton Citeureup Elevated Construction Project Data.
Diasanto, 2008, Comparison of Superstructure Costs Between Using Conventional Methods and Precast Methods Using Bolted Connections, in the Rusunawa Project, Cimahi-Bandung,Thesis, University of Indonesia, Jakarta
El Sayary, S., & Omar, O. (2021). Designing a BIM energy-consumption template to calculate and achieve a net-zero-energy house. Solar Energy, 216, 315–320. Accessed Februari 2022. https://doi.org/10.1016/j.solener.2021.01.003
Fakhruddin, et.al., (2019). Dissemination of Building Information Modeling (BIM) Technology Applications in the Indonesian Construction Sector.Journal of Applied Technology for Community Service (TEPAT), 2(2). Accessed Januari 2022. https://eng.unhas.ac.id/tepat/index.php/Jurnal_Tepat/article/view/82/49
Raflis, Yuwono, B. E., & Rayshanda, R. (2018). Benefits of Using Building Information Modeling (BIM) in Construction Projects as Stakeholders Communication Media. Jurnal Construction Engineering and Sustainable Development (CESD), 1(2), 62–66. Accessed Mei 2022. https://www.researchgate.net/publication/341402841
Suherman, Tata, 2022, Interview result, Supervisor of PT Wika Beton Elevated Construction Project
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 Ari Yulitasari, Alip Prajoko, Abdul Mubarak, Edison Hatoguan Manurung

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.